LEVY OF GST ON LIQUIDATED DAMAGES

Levy of GST on liquidated damages has been a debatable issue. Section 7(1) (d) of the GST Act, 2017 includes activities referred to in Sche...
Levy of GST on liquidated damages has been a debatable issue. Section 7(1) (d) of the GST Act, 2017 includes activities referred to in Schedule II in the scope of supply. Entry 5(e) thereof declares that “agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act” shall be treated as supply of service. The view supporting levy of tax on liquidated damages and forfeiture of earnest money is based on premise that the party has ‘tolerated’ the non-performance. 



Meaning of Liquidated Damages: 

Black’s Law Dictionary (Tenth Edition) on page 473 defines Liquidated damages thus: 

“An amount contractually stipulated as a reasonable estimation of actual damages to be recovered by one party if the other party breaches. If the parties to a contract have properly agreed on liquidated damages, the sum fixed is the measure of damages for a breach, whether it exceeds or falls short of the actual damages.” 

The distinction between a penalty and genuine liquidated damages, as they are called, is not always easy to apply. In the first place, if the sum payable is so large as to be far in excess of the probable damage on breach, it is almost certainly a penalty. Secondly, if the same sum is expressed to be payable on any one of a number of different breaches of varying importance, it is again probably a penalty, because it is extremely unlikely that the same damage would be caused by these varying breaches. 


See citation below definition of ‘liquidated damages’ in Black’s Law Dictionary (Tenth Edition) 


Why liquidated damages: 

Performance is the essence of a contract and hence parties to contract generally incorporate their expectation in terms of damage caused by failure of either party to perform its obligations completely or as per the agreed terms. The contract may prescribe damages for deficiency in the performance of contract known as ‘liquidated damages’. It is to dissuade unsatisfactory performance or non-performance. For instance, contracts state that time is the essence of contract, and any delay invites, say, 1% of the value of the contract for every week of delay and the like. Other examples may be rent for delay in lifting goods; breach of agreement for not accepting alternate employment offer from competitor up to a stipulated period of time and so on. 


Liquidated and unliquidated damages : 

Liquidated damages (also referred to as liquidated and ascertained damages) are damages whose amount the parties designate during the formation of a contract for the injured party to collect as compensation upon a specific breach (e.g., late performance). Liquidated damages clauses are used in many types of contacts, most frequently in IT and construction contracts. Including a liquidated damages clause in a contract provides certainty to the parties, facilitates the recovery of damages by avoiding the requirement of proof of loss, simplifies the dispute resolution procedure and may induce performance of a contract. Liquidated damages clauses regulate the rights of parties after a contract is breached, or alternatively quantify the party’s secondary obligation to pay damages (which survives termination). 

Unliquidated damages is not pre-fixed or determined. A claim for unliquidated damages is governed by common law. When damages are not predetermined/ assessed in advance, then the amount recoverable is said to be 'at large' (to be agreed or determined by a court or tribunal in the event of breach). For example, in a personal injury lawsuit, the exact amount of an award for actual and punitive damages aren’t known and can’t be calculated at the time of filing. Black’s Law Dictionary (Tenth Edition) on page 475 defines unliquidated damages thus: 

“Damages that cannot be determined by a fixed formula and must be established by a judge or jury.” 

Sometimes liquidated damages clauses in contract provide for ‘NIL’ or ‘N/A’ for rate of liquidated damages. There have been varied line of judicial thinking on interpretation of ‘NIL’ or ‘N/A’ clause for liquidated damages. 

Court in Australia(1 J-Corp Pty Ltd v Mladenis (J-Corp) (2010) 26 BCL 106 ) took the view that use of ‘NIL’ did not exclude right to claim unliquidated damages. The court emphasised that ‘clear words’ are required to rebut the presumption that a contracting party does not intend to abandon a common law breach of contract remedy. The liquidated damages clause here read as “If the builder breaches sub-clause 11.1, it shall be liable to pay the Proprietor liquidated damages at the rate of NIL Dollars ($00.00) per day for each day beyond the due date for practical completion until practical completion is deemed to have taken place.” The Court found that the clause here did not contain clear words to express the intention that the owner could not claim unliquidated damages; it only provided that no liquidated damages could be claimed. 



In a leading English case(Temloc Ltd v Errill Properties Ltd (1987) 39 BLR 30 ), unliquidated damages were excluded by the use of ‘£ NIL’ as the rate of liquidated damages. The Court decided that the liquidated damages clause was an exhaustive agreement for the treatment of damages. As the parties agreed that damages for late completion were to be liquidated damages, it could not have been intended that the Principal should also be allowed unliquidated damages. 



So far as the law in India is concerned, there is no qualitative difference in the nature of the claim whether it be for liquidated damages or for unliquidated damages. Section 74 of The Indian Contract Act, 1872 eliminates the some-what elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages 'and stipulations in the nature of penalty. Under the common law a genuine pre-estimate of damages by mutual agreement is regarded as a stipulation naming liquidated damages and binding between the parties. A stipulation in a contract in terrors is a penalty and the Court refuses to enforce it, awarding to aggrieved party only reasonable compensation. The Indian Legislature has sought to cut across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty, and according to this principle, even if there is a stipulation by way of liquidated damages, a party complaining of breach of contract can recover only reasonable compensation for the injury sustained by him, the stipulated amount being merely the outside limit.1 

View supporting levy of GST on Liquidated Damages: 

The view supporting levy of tax on liquidated damages is based on premise that the party has ‘tolerated’ the non-performance. 

‘Tolerate’ is ‘verb’ for ‘noun’ ‘toleration’. ‘Toleration’ is defined in Black’s Law Dictionary (Tenth Edition) on page 1716 as 

“1. The act or practice of permitting or enduring something not wholly approved of; the act or practice of allowing something in a way that does not hinder. 2. The allowance of opinions and beliefs, esp. religious ones, that differ from prevailing norms…..” 

Erstwhile service tax regime, through the concept of declared service, levied tax on “agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act.”2 

Authorities administering the law have taken a view that payment of liquidated damages or fine for non-performance of a contract is an activity liable to tax. Entry 573 in Notification number 25/2012-Service Tax dated June 20, 2012 provided for exemption in respect of “Services provided by Government or a local authority by way of tolerating non-performance of a contract for which consideration in the form of fines or liquidated damages is payable to the Government or the local authority under such contract” GST Act has continued with the scheme of taxation and exemption under Service Tax law. Entry 5.(e) in Schedule II of the GST Act is identically worded and declares that “agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act” shall be treated as supply of service. 

Notification number 12/2017-Central Tax (Rate) dated June 28, 2017 provides for exemption from tax. Relevant entry in the said Notification reads thus: 

Sl.No.
Chapter,
Description of services
Rate
Condition

Section,

(per


Heading, Group

cent.)


or Service Code




(Tariff)








77
Heading 9991
Services provided by the Central Government,
Nil
Nil

or
State Government, Union territory or local



Heading 9997
authority by way of tolerating non-




performance of a contract for which




consideration in the form of fines or liquidated




damages is payable to the Central Government, State Government, Union territory or local authority under such contract.



1 Union of India v Raman Iron Foundry, AIR 1974 SC 1265; 1974 SCC (2) 231 
2 Section 66E(e) of the Finance Act, 1994 
3 Inserted by Notification number 22/2016-Service Tax dated April 13, 2016 

In a matter before the Maharashtra Authority for Advance Ruling in the case of Maharashtra State Power Generation Company Limited 2018-TIOL-33-AAR GST1 on applicability of GST on Liquidated damages under the phrase ‘agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act’ appearing in clause (e) of para 5 of Schedule II of the GST Act, the taxpayer had contention that 

  • 1. There is no explicit agreement between the company and the contractor wherein the company is intending to supply service of tolerance of delay. 
  • 2. The delay is neither desired by the company nor by the contractor but to impress upon the contractor to adhere to timelines. 
  • 3. Payment of damages, deducting the liquidated damages or the forfeiture of deposit does not restitute the person to whom loss or damage is caused. 
  • 4. Liquidated damages are in nature of a measure of damages to which parties agree, rather than a remedy. 
  • 5. By charging damages or forfeiture, one party does not accept or permit the deviation of the other party. It is an expression of displeasure. 
  • 6. Liquidated damages cannot be said to be the desired income, it is the compensation for loss suffered by recipient. 
  • 7. Damages are not received by the person for the tolerance of an act, but it is made to compensate the loss suffered. 
  • 8. Recovery of liquidated damage is not for supply of service for tolerance of an act. The word ‘obligation’ used in clause clearly means that person should undertake to tolerate an act. There should be a contract for the said purpose and the consideration should be received for such an act of tolerance. 
  • 9. Under the Australian GST, it has been clarified that if clause relating to early termination has been specified in the original contract of lease and early termination has been in accordance with the said contract then termination payment will be considered as change of consideration of earlier supply (i.e. redetermination of consideration). It will not be considered as separate supply, but will be considered as adjustment even in relation to that earlier supply. 

The Authority however held that tax was payable on Liquidated damages observing that 

  • 1. The value of work done and which is to be paid is not effected by the amount deducted therefrom towards liquidated damages. Thus the consideration for work done remains unaltered. 

  • 2. The act of delayed supply has happened. The same is being tolerated by an additional levy in the nature of liquidated damages. 

  • 3. The impugned income though presented in the form of a deduction from payments to be made to the contractor is the income of the applicant and would be a supply of ‘service’ in terms of clause (e) of para 5 of Schedule II of the GST Act. 

1 [2018] 13 GSTL 177 (AAR-GST) ruling dated May 08, 2018 

In yet another matter1, the same authority held that the act of vacating rented premises for redevelopment as per the redevelopment agreement is agreeing to the obligation to refrain from an act or tolerating an act or situation of redevelopment in place of old premises and of not causing hindrance or creating obstacles in the same. 

Above understanding of sub-ordinate legislature and also of quasi-judicial authorities leads to undefined or boundary less expanse of entry “agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act.” 

View opposing levy of GST on Liquidated Damages: 

It is settled law that an exemption entry cannot presuppose the existence of levy.2 An exemption notification clearly is not a charging provision and it cannot be interpreted so as to create a duty liability where none existed under the Act (Tariff entry)3. 

The purpose of agreeing to payment of liquidated damages is to ensure performance. It cannot be said to be a consideration for tolerating non-performance. On the face of it, payments of compensation or damages are not consideration for supplies for tax purposes. This is because they invariably amount to financial settlement of losses caused by breach of agreement or infringement of rights rather than the provision of goods or services. Payment of damages or the forfeiture of deposit does not restitute the person to whom loss or damage is caused. Liquidated damages are in nature of a measure of damages to which parties agree, rather than a remedy. By charging damages or forfeiture, one party does not accept or permit the deviation of the other party. It is an expression of displeasure. Liquidated damages cannot be said to be the desired income or result of the contract. Liquidated damages are recovered for compensating the loss suffered by the recipient. Section 73 and 74 of the Indian Contract Act, 1872 provide for recovery of liquidated damages in case of breach of contract. 

Liquidated damages whether re-determination of consideration: 

There is one school of thought that levy of liquidated damages in effect reduces the consideration for supply. Thus, it is re-determination of price of supply. Under Australian GST, in one of the Commissioner’s ruling relating to payment on early termination of lease of goods, it was clarified that if clause relating to early termination has been specified in the original contract of lease and early termination has been in accordance with the said contract then payment will be considered as change of consideration of earlier supply (i.e. re-determination of consideration). It will not be considered as separate supply, but will be considered as adjustment event in relation to that earlier supply. Thus, Australian GST has treated the payment of liquidation damages as part of the same supply and mere re-determination of the consideration of the same supply if it has been specified in the original contract i.e. if liquidation of damages are to be borne by the service provider then same will be considered as towards deficiency of services and thereby reduces the original consideration and it will not be considered as separate service and hence it is not covered by the term ‘obligation to tolerate an act or a situation’.1 

1 In Re: Zaver Shankarlal Bhanushali 2018-TIOL-84-AAR-GSR ruling dated May 22,2018 

2 Commissioner of Central Excise and Customs, Kerala and Others v Larsen and Toubro Limited and Others [2015] 84 VST 403 (SC); [2015] 39 STR 913 (SC); 2015-TIOL-187-SC-ST para 44 – “We have been informed by counsel for the revenue that several exemption notifications have been granted qua service tax "levied" by the 1994 Finance Act. We may only state that whichever judgments which are in appeal before us and have referred to and dealt with such notifications will have to be disregarded. Since the levy itself of service tax has been found to be non-existent, no question of any exemption would arise.” 

3 Kiran Spinning Mills,Thane v Collector of Central Excise, Bombay-II [1984] 17 ELT 396 (Tri-Delhi)(SB). Revenue’s appeal against this judgment was dismissed by the Supreme Court in Collector of Central Excise, Bombay v Kiran Spinning Mills [1988] 34 ELT 5 (SC). 

Is GST leviable on Unliquidated Damages, penalties etc: 

Penalties may be statutory such as penalty for late filling of tax returns, penalty for over speeding on a public road. Penalties may also be private such as loan prepayment penalty, penalty for wrong parking or not wearing helmet in an industrial township and so on. As discussed earlier, unliquidated damages are in the nature of penalty. 

Black’s Law Dictionary (Tenth Edition) on page 1313 defines ‘penalty’ as “punishment imposed on a wrongdoer, usually in the form of imprisonment or fine; especially, a sum of money exacted as punishment for either a wrong to the state or a civil wrong (as distinguished from compensation for the injured party’s loss). Though usually for crimes, penalties are also sometimes imposed for civil wrongs.” 

CBEC Education Guide, at the time of introduction of Negative list based taxation of services2, in para 2.3.1 explained that “to be a service an activity has to be carried out for a consideration. Therefore fines and penalties which are legal consequences of a persons’ actions are not in the nature of consideration for an activity.” Frequently Asked Questions on applicability of GST on Banking, Insurance and Stock Brokers Sector released by CBIC in June, 2018 through question 49 has clarified that “fines and penalties are imposed for breaking the law by a person. 

They are not in the nature of a consideration for an activity and hence, would not constitute a supply of service.” 

Breach of contract is between the two contracting parties, whereas breach of law is one between a citizen and the Government. The question whether any impost is in essence compensatory or is by way of penalty will have to be decided having regard to the relevant provisions of the law under which it is imposed and the circumstances under which it has been imposed. The mere nomenclature as interest, penalty or damages in the relevant Act may not conclusive. Expenditure for violating traffic rules by entering town on no entry times, one way traffic violation, penalty imposed by police in the course of regulating traffic all are in the nature of penalty. 

Whenever certain damages are to be paid for the breach of a contract, such damages are treated to be normal incidences of business. Extending this logic, charges levied by airlines/ railways/hotels for cancellation of bookings as per terms of contract are not penalty, even if described as such. Similarly payments made for regularising certain deeds/ events on payment of prescribed fees are not penalty. 


  • 1 See arguments from taxpayer in proceedings before The Maharashtra Authority for Advance Ruling in the matter of Maharashtra State Power Generation Company Limited 2018-TIOL-33-AAR GST; [2018] 13 GSTL 177 (AAR-GST) ruling dated May 08, 2018 
  • 2 TRU Circular dated June 20, 2012 
  • 3 Judgment dated January 9, 2009 
In Kaira Can Company Ltd v DCIT [2010] 127 TTJ 514 (ITAT-Mumbai)3 the assessee made certain payments to SEBI under a scheme framed by SEBI to regularize default of certain disclosures under SEBI Substantial Acquisition of Shares and Takeovers) Regulations, 1997. Revenue disallowed these payments as expenditure holding them hit by explanation to section 37(1) of the Income-tax Act, 1961. The Tribunal held that such payments cannot be said to be a penalty under section 15A of the SEBI Act hence not hit by explanation to section 37(1) of the Income-tax Act. 

In Ashok Kumar Damani v Addl CIT [2011] 130 ITD 287 (ITAT-Mumbai)1 the assesse made short payment of margin money to the stock exchange. The penalty levied by the stock exchange for the same was paid by the assesse during the period under consideration. The AO disallowed the same on belief that the said expenditure is not an allowable expenditure being in the nature of penalty. It was held by the Tribunal that the payment had been made to stock exchange on account of short payment of margin money. This is only a compensatory payment under the rules of the stock exchange which is allowable as revenue expenditure as the same is not for infraction of law. 

In Agarwal Roadlines P Ltd v Dy. Comm. of Income Tax [2010] 129 TTJ (ITAT-Ahemedabad) (UO) 492 the assessee paid overloading charges under a scheme of ‘Gold Card’ introduced by the Government of Gujarat which allowed carrying excess load in vehicle on payment of additional fees fixed for that gold card. Revenue contended that carrying overloaded goods being a cognizable offence and infringement of law and payment being penal in nature and not incidental to the assessee’s regular business, the same is liable for disallowance. The contention of the asseessee was that this expenditure is incurred in the normal course of business and corresponding income out of carrying of overload was subjected to tax as the party was billed as per tonnage carried. It was further contended that overloaded vehicles were not detained or confiscated even when overloading was done on regular basis. These were allowed to ply if overloading fee was paid. The Tribunal held that such fees was compensatory in nature and not penal. Payment of this fees entitled transporters to carry over load to final destination without stopping them to unload the excess weightage. The fact that excess weight was not required to be unloaded demonstrates that payment under the scheme was compensatory and not penal as no Government machinery would encourage violation or infringement of legal provisions. Expenditure incurred was allowed as deduction. 

Post GST Act amendment: 

Schedule II of the GST Act was supposed to be mere an authoritative declaration as to nature of activity, whether it entails supply of goods or services. However, its positioning in definition of supply as clause (d) of sub-section (1) of section 7 of the GST Act made all the items listed in the Schedule ‘supply’. This also led to several unintended conflicts in the scheme of Act. 

1 9 taxmann.com 69 - AY 2005-06 judgment dated December 3, 2010 
2 A.Y.2005-06 judgment dated September 18, 2009 


The Lok Sabha on 9th August, 2018 has passed four amendment bills relating to GST. Section 7 of the CGST Act, 2017 defining ‘supply’ is being amended w.e.f. 1st July, 2017 itself. A new sub-section (1A) is inserted in section 7 and clause (d) of sub-section (1) is omitted. Thus now the role of Schedule II will be limited to classification of supply as ‘goods’ or ‘service’. For levying tax on liquidated damage, transaction will have to first pass the test of supply, which appears to be a difficult proposition. Erstwhile service tax law, on introduction of negative list based taxation, declared activity of ‘agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act’, to be a service. GST law does not make any such declaration. It merely classifies supply as ‘goods’ or ‘services’. Though levy of tax on these activities were not free from doubt in service tax law, under GST it is more doubtful as there is no such statutory declaration. Liquidated damages may hardly satisfy the essentials of supply of service. 

It is settled law that mere mention of an item in the Tariff, does not make the same as taxable. In Commissioner of Central Excise, Chandigarh-I v Markfed Vanaspathi and Allied Industries [2003] 4 SCC 1841 the Court held that twin tests of ‘manufacture and marketability’ do not cease to apply if a good falls within a tariff entry, under Excise law. The Andhra Pradesh High Court in State of Andhra Pradesh v BSNL [2012] 49 VST 982 held that entry for recharge coupons in Schedule under the VAT Act represents sale of the recharge voucher, to the service provider, and not to the transaction between the service provider and the subscriber even if, in the process, the recharge coupons are routed through various distributors. Thus the Court held that tax can be charged only on paper value of the recharge voucher. The Division Bench of Karnataka High court in Sasken Communication Technologies Ltd v Joint Commissioner of Commercial Taxes Bangalore [2012] 55 VST 89 (Kar)3 held that entry number 11 in sixth Schedule to the Karnataka VAT Act, 2003 reading as ‘Programming and providing of computer software’, which purported to include this activity within the meaning of term ‘works contract’ for the purpose of levy of Vat was bad in law. It was held that State Legislature is competent to enact laws in respect of sale of goods. By introducing a schedule to the said enactment and describing under a works contract ‘programming and providing a computer software’, unless the said works contract involves an element of sale of goods, the State Legislature has no power to levy tax under the said Act. 
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx 

Acknowledgements 

CA Sanjay K. Agarwal has  drafted this article and CA. A. Jatin Christopher has reviewed the same

COMMENTS

BLOGGER
Name

. SECURITIES,5,(MNP),2,(TDS)2007-08,1,`,1,01.07.12,23,01.09.2008,1,01.10.2012,2,06.07.2009,3,07.08.2012,1,1 PERCENT EXCISE ITEMS LIST,2,1 sep,1,1% excise,2,10 year nsc,7,10(10C),1,10(10D),1,10(11),1,10(12),1,1000 court cases judgements supplied to ITO,7,1000 rupee note,3,11-2008,1,11-2010,1,111A,4,130 items,1,14.08.2008,1,15 august,2,150 Rs coin,2,15g,14,15h,15,18-12-2009,1,192(1A),5,192A,2,194 I,4,194 IA,1,194A,7,194c from 01.10.2009,7,194H,6,194j,15,194LC,3,194N,1,194O,1,194q,2,1981-2007,2,2% cst,1,2% excise,1,2004,1,2008,1,2008-09 FY,1,2010,2,206AA,14,234A 234B 234C,10,234c interest calculator,11,234D,1,234E,16,234F,2,23AC,1,23ACA,1,23B,2,24C,3,24q annexure II,5,25 paisa coin,1,271(1)(c),5,271B,2,271H,4,272B,1,27A,1,280,5,280 challan,4,281,4,282,2,283,2,29 AUGUST,2,29.04.2010.,1,29/08/2008,2,29/2008 service tax,2,2g meaning use,1,3 idiots,1,30 MARCH,4,31st March,19,32-2010,1,33 of 2009,1,35(2AA),1,35(2AB),1,3CD,18,3g meaning use,1,40(b),4,43B,5,44 AB EXEMPTED INCOME,1,44AA,1,44AB AGRICULTURE,2,44AB new limit,29,44AB NON RESIDENT,3,44ad,20,44ada,5,46/2012 45/2012,1,49C,1,5 day week,1,5 years post office deposit,5,5/2011,1,50 paisa coin,2,500-1000 notes banned,128,54b,19,54EC,28,54ee,1,54f,22,54gb,1,5th paycommission punjab,1,6 % excise,1,6 crore advance limit,1,6/2005,1,69/2010,1,6th cpc,5,6TH PAY COMMISSION,6,70% of pan etds,7,7th Central Pay Commission,12,8 tips to save tax,2,80C,90,80ccc,3,80CCD,17,80cce,2,80CCF,18,80CCG,6,80d,10,80DDB,14,80EE,4,80EEA,1,80G,6,80GG,8,80GGA,6,80GGB,1,80ggc,1,80tta,5,80TTB,3,80U,2,85% of pan etds,1,86/2008 DATED 13-08-2008,1,87A rebate,11,89(1),23,89(1) relief calculator,20,9.5 % rate for private epf,8,92E,1,95% of pan etds,5,98 dated 04/01/08,1,aadhaar,18,aakash tablet,1,aam admi,1,aar,4,Aayakar Sampark Kendra,1,abatement,13,abolished,1,ACCOUNT PAYEE DRAFT,2,Accounting,1,ACCOUNTING CODE,11,accounting code for services,6,ACCOUNTING FOR GOVT GRANTS,3,accounting standards,12,ACES,10,ADD IN,1,Add-Ins,2,additional relief in budget 2010,1,adjustment of advance FBT with advance Tax,2,advance rullings,3,advance salary,2,advance tax,2,ADVANCE TAX CALCULATOR,10,advance tax challan,19,advance tax collections,1,ADVANCE TAX CUT OFF AMOUNT,12,ADVANCE TAX DATES,20,AFFIDAVIT,2,affordable housing,1,AG Projects Technologies Ltd RT,1,age 80 addition pension,2,aibea wage revision,1,aibea wage revision latest news,1,aiboa,1,aiboc,1,aiboc wage revision,1,AIG,1,AIR,10,airline ticket booking tds,7,airlines,3,AIS,4,all is well,1,allowances,5,allownces,4,alphabet of inspiration,1,alteration on check allowed,3,alternate minimum tax,4,AMENDED 3CD,12,amendment in companies bill 2011,2,amendment in gratuity act 2010,5,amendment in registration service tax,4,AMENDMENT IN SERVICE TAX ON RENT,6,amendment to finance Bill 2010,1,AMNESTY SCHEME 2007,2,amt,2,Anna Hazare,2,anna hazzare bill vs govt lokpal bill,1,annual information statement,1,appeal,15,apply for new pan card against old pan card,3,aqb,1,arbitration,2,arrears of salary,5,arrears of sixth pay,6,ARRERS TAX,2,AS-12,1,ASBA,1,assessee in default,2,ASSESSMENT REOPENING,8,ASSESSMENT YEAR 2008-09 REFUND,1,atm,13,atm 100 per day,2,atm cash without card,2,atm tips,9,atm wrong debit,1,audit cases itr filing,2,audit limit enhanced,13,Audit Questionaire,1,AUDIT REPORT,63,AUS VS IND.INDIA VS SL,1,Automated teller machine,1,AUTOMATION OF CENTRAL EXCISE AND SERVICE TAX,7,Axis Bank credit cards,2,ay 2010-11,1,bad debts,2,Balwant Jain,180,Bank,6,Bank account,15,bank audit,3,bank audit 2012,1,bank charges,19,BANK SALARY,2,bank strike 06/07/09 and 07/07/09,1,banking law amendment,1,banknotes,6,banks npa provisioning,4,BARE ACT,4,bare rules,1,BASE RATE BY BANKS,2,bcct,1,belated return,3,benami property,1,BIMAL JAIN,476,biometric pan card,3,black and white form not acceptable,2,black money,27,BLOCK PERIOD,1,blogging,1,bobay refund,1,BONUS,2,bonus share,2,book discount,5,BOOK ON EFILING,1,BOOK REVIEW,1,books of accounts,6,BOOMING INDIAN ECONOMY,3,both House rent allowance,11,both hra and house loan,15,Brass Scrap,3,BROKER,3,BSE,1,bsnl broadband,1,bsnl broadband usage,1,bsnl land line sms alert,2,BSR CODES,3,BUDGET 2009,18,budget 2010,28,budget 2010-11,4,budget 2011,13,BUDGET 2012,38,budget 2013,17,BUDGET 2014,39,BUDGET 2014 CONTEST,6,budget 24-25,5,budget expectations,8,BUDGET HIGHLIGHTS,11,budget live on computer,5,budget live telecast,5,budget notification,1,budget on tv,1,budget speech,16,BUDGET SPEECH DOWNLOAD,2,Budget-2014,2,Budget-2015,45,BUDGET-2016,71,budget-2017,28,BUDGET-2018,32,BUDGET-2019,22,BUDGET-2020,2,budget-2022,9,Budget-2026,5,BUDGET-21,39,Budget-23,51,Budget-25,20,BUDGET08,5,BUDGET2018,1,budgeting,2,Business,5,BUSINESS AND PROFESSION MEANING,1,BUSINESS COVERED UNDER 44ab,2,buy back,2,BUY HOUSE,5,C FORM,5,CA CAN ONLY AUDIT MVAT,4,CA CLUB INDIA,1,CA GIRISH AHUJA,3,CA NITIN GUPTA,5,CA PARDEEP JAIN,5,CA ROHIT GUPTA,4,ca services,3,CA sudhir Halakhandi,1,CA Swapnil Munot,15,CA Vikas Khandelwal,9,calculate arrear,2,CALCULATE NEW PAY,2,calculate your emi,4,calculation of tax on salary arrears,4,CALCULATOR,75,CALCULATOR REVISED,1,capital asset,4,capital formation huf,3,Capital gain,47,capital gain account scheme 1988,11,CAPITAL GAIN INDEX,30,capital gain on repayment of loan,2,capital gain on tenancy rights,1,capital goods,3,capital revenue,1,CAPITAL SUBSIDY,3,CAR LOAN,1,CAR LOAN RATE INCREASE,12,carry forward of losses,1,carry forward of losses in late return,5,cas,1,cash back,1,Cash credit,2,cash flow statement,1,CASH PAYMENT DIS ALLOWANCE,12,CASH PAYMENTS EXCEEDING 20000,6,CASH SUBSIDY,3,Cash Transaction 2016,8,cbdt,15,cbec,9,centeral sales tax rate,2,CENTRAL PAY COMMISSION,6,CENTRAL PROCESSING CENTER,2,CENTRALISED PROCESSING OF RETURNS,1,Cenvat,63,CENVAT Credit Rules,81,cgas 1988,3,challan,7,challan 281,10,CHALLAN 289,1,challan correction,8,challan Form 17,11,CHALLAN STATUS INQUIRY,1,change,1,change in cst rate,5,change in excise duty rates,11,CHANGE IN PAN ADDRESS,3,CHANGE IN PAN DATA,7,change in tds rates in budget,14,changes,2,CHANGES IN SERVICE TAX ACT,58,changes in Gst,1,changes in income tax,2,changes in new itr forms,12,CHANGES IN TDS,16,CHARGES ON CASH PAYMENT OF CREDIT CARD BILL,3,charitable organisation,5,check name from PAN,2,check tds deducted online,3,Cheque,12,cheque bounce,7,cheque payment before due date,8,cheque tender date /realisation date,4,Cheque Truncation,7,CHEQUE VALIDITY,9,child care leave,3,CHILD DEPENDENT PREMIUM,1,CHILD MARRIED PREMIUM,1,child plan,1,childeren name,1,children education allownces,10,chip based atm card,4,cibil,13,cibil for companies,5,CII 2007-08,1,CII 2008-09,2,CII 2010,1,cii 2012-13,1,CII2011-12,1,cin,2,CIRCULAR 3/2010 DT 2.03.2010,1,CIRCULAR 8-2010,1,CIT v. Emilio Ruiz Berdejo (2010) 320 ITR 190 (Bom.),1,cloning of atm card,1,clubbing of income,6,co-ownership,2,COLLECTION CHARGES,1,COLOR SCHEME,1,COMMISSION ON SMALL SAVINGS,2,common error in 2009-10,1,common error in itr 4-5-6,3,compa,1,companies bill 2012,2,COMPANIES RATE,2,COMPANY BILL 2011,6,company deposit,5,Company Law Settlement Scheme,5,COMPANY REGISTRATION,4,complusory payment of taxes,1,Composite rent,1,COMPOSITE SUPPLY,3,Composition scheme GST,15,Composition scheme service tax,2,compounding,2,compounding of offence,1,COMPUTER AS FAX MACHINE,1,computer sytem at ito office,1,CONCEPT PAPER,1,configure yahoo mail in outlook express,7,consolidate account statement,5,construction purchase of house,9,Consultancy Service,2,consumer loans,2,Consumer Price Index,2,consumer protection,1,continues services,1,CONTRIBUTION TO NEW PENSION SCHEME,10,CONTRIBUTORY PENSION FUND,3,CONVERT FIGURES INTO WORD EXCEL,8,COPARCENER,1,CORONA,8,CorpMcash,1,Corporate Social Responsibility,1,corporate tax,1,corporation bank,3,correction etds,10,CORRECTION IN PAN DATA,8,correction in section,4,CORRECTION RETURN,6,CORRECTION RETURN.ETDS,7,cost accounting,5,cost audit,6,cost inflation index,21,cost inflation index 2012-13,2,COST INFLATION INDEX FY 2010-11,1,COST INFLATION INDEX FY 2011-12,1,COST OF INDEXATION CALCULATOR,5,court case in entry tax punjab,2,covid-19,3,cpc phone number,6,cpf,7,Credit card,32,CREDIT CARD BILL PAYMENT ICICI BANK,6,credit scores,14,cricket team,1,critical illness,1,CROSSED DEMAND DRAFT,2,CRR,14,crr reducred,1,cryptocurrency,1,CS DIVESH GOYAL,69,CST,12,CST 3% OR 2 %,3,cst act 1956,1,cst form,6,CST FORM STATUS,1,cst rate changed,3,CST REDUCE RATE,4,ctt,3,currency,2,CURRENCY TRADING ILLEGAL,1,custom,4,custom changes in budget,18,cusual leave,1,DA MERGE,2,da rate,16,da rate 01.07.2012,4,da rate january 2013,4,da rate july 2012,3,da rate wef 01.01.2012,4,date extension,4,DDO ASK RENT RECIPT,1,ddt,4,dearness allowance,15,Debit card,11,DEBT EQUITY RATIO,1,debt funds,14,debt trap,3,declared goods,1,DEDUCTION 80C,6,deduction for higher studies,3,deduction on saving bank interst,2,deduction u/s 80DD,6,Deemed income of employee,1,deemed ownership,2,deemed services,1,defective return,5,defence officers,1,defence pay,1,defence pay scales,2,DELAY IN FILING,3,delete ledger in tally,1,DELHI HIGH COURT,11,demat,4,deposit tax of two quarter in single challan,3,depreciation,15,depreciation on car,3,depreciation on commercial vehicle.,2,DEPRECIATION ON INTANGIBLE ASSETS,3,depreciation rate,13,depreciation rate 2009-10,3,DETAIL AFTER E FILLING,1,DETAIL OF TIN,1,Determination of value,1,DIFFRENT TYPE OF TAXES,1,digital signature,10,din,4,direct payment in bank account,1,DIRECT SUBSIDY,10,direct tax bill,6,direct tax changes in budget,26,direct tax code,39,direct tax code 2009,6,dis,1,Disability insurance,4,discussion Paper,4,distribution of salary,2,dividend distribution tax,2,dividend striping,1,dnd,1,do not call.,1,document identification number,1,document ientification number,1,documentaion of ITR,1,documents required for service tax registration,5,domestic transfer pricing,5,donation,3,dot,1,double taxation,1,dow jones,1,download,1,download 89(1) relief calculator,13,download direct tax code 2012,10,download form 16A,7,download fvu,28,download idfc INFRA BONDS FORM,1,draft reply,1,drawback rates,2,dtaa,4,dtc,10,DUE DATE AY 2010-11,2,due date ay 2011-12,3,due date extended,73,due date extended to 31.08.2012.,2,due date for service tax return,36,due date form 16,21,due date form 16a,10,due date June,2,due date march tax,11,due date of return 2008-09,3,due date pf esi,6,due date to deposit tds,15,DUE DATES,19,DUE DATES CALENDAR,8,DUE DATES CALENDER,9,DUE DATES INCOME TAX,24,DUE DATES SERVICE TAX,42,DUE FAMILY PENSION,1,DULICATE PAN,1,DUPLICATE TAN,5,dvat,8,e book Income Tax rules,3,e book on service tax,22,E ERA OF TAXES,1,e filing do and don'ts,7,e filing of audit report,10,e filing processing status,8,e filing software excel free,4,e filing through evc,10,e filing utilities,6,e mode for notice to shareholder,1,e notice to share holder,1,e payment of epf,5,E PAYMENT OF EXCISE DUTY,2,e payment of income tax,5,E PAYMENT OF SERVICE TAX,4,e payment of tds,8,E STAMP DUTY,1,e tutorial for TAN registration,3,E-1 FORM,1,E-1 SALE,6,e-commerce,1,E-FILE SERVICE TAX RETURN,18,e-Intermediary,1,e-payment from friends account,2,E-PAYMENT OF SERVICE TAX,9,e-payment of taxes,6,E-SEVA BY ICAI,4,e-TDS/TCS statements,2,E-WAY-BILL,15,earn from home,1,earned leave,2,Easy Exit Scheme,1,ebay,1,EBOOK,75,EBOOK ON SERVICE TAX,23,ECH mandate,1,economic survey,9,economic survey 2010,3,economic survey 2011,2,economic survey 2012,1,Edible Oils,1,EDITABLE INCOME TAX FORM,1,education cess,6,EDUCATION LOAN,5,eet,4,EFFECTIVE DATE CST RATE REDUCTION,2,effective date of allowncs,2,efiling errors,5,efiling free,2,efiling income tax return,31,efiling of excise return,6,efiling registration problem,18,electric vehicle,1,Electricity act,2,ELECTRONIC FOREX TRADING,1,Electronic Gold Receipts,1,Electronic Verification Code (EVC),11,elegent card on holi,1,ELSS,20,EMANAGEMENT OF TAXES,1,emergency fund,1,EMI CALCULATOR,8,empanelment as branch auditor,2,EMPLOYEE PROVIDENT FUND,10,employee state insurance,2,employee state insurance act 1948,1,employee state insurance act Limit,1,employer e sewa,4,eMudhra Consumer Services,1,entries r off in 50 paisa,1,entries rounded off in rs,1,ENTRY TAX,5,entry tax punjab,2,epf,57,epf challan,33,epf claim,12,epf e passbook,8,EPF FAQ,33,epf int rate 11-12,6,epf interest exemption,11,epf interest rate,25,epf interest rate for fy 2010-11,8,epf limit,8,epf online,12,EPF ONLINE CHALLAN GENERATION,4,epf statement,6,EPF TRUST,1,epf withdrawals,12,epfo,44,equal monthly installments,2,equity funds,7,ER-1,2,ER-2,2,er4 form online,1,error in etds return,10,error in st-3,5,esi,8,esi contribution,3,esi limit 10000,1,esi limit 15000,4,esi limit from 01.05.2010,1,esi return,1,ESOP,5,ETABF,1,ETAX,2,etcs,10,etds,33,etds correction,17,etds defualts,2,etds due date,9,ETDS FVU 3.1,3,ETDS PAYMENT,3,ETDS Q4 ANN II,3,etds retur with insufficient pan,2,etds return,25,ETDS RETURN DUE DATES,24,etds return less deduction of tax.,2,ETDS RTEURN SOFTWARE,2,etds software,5,etds without pan,5,etrip,1,Excel,11,EXCEL 280,2,excel add in,1,EXCEL CII,5,excel form 16,10,EXCEL SHORT CUTS,9,excel software,2,excell add in,4,EXCESS TDS,7,Exchange-traded fund,3,exci,1,excise,10,excise changes in budget,19,EXCISE FORMS,1,excise notification,2,Excise on branded goods,2,excise on utensils,1,excise rate reduced,4,EXCISE REGISTRATION,5,exclusion from capital asset,1,exempted capital gain,6,EXEMPTION GST,3,exemption limit increased,4,EXEMPTIONS IN FEW SERVICES,2,exice duty on new items,1,EXIDE CASE CALKUTTA HIGH COURT,2,EXPANSION OF EXISTING SERVICE,1,EXPLANATORY NOTES TO FINANCE ACT(2) 2009,1,export,21,EXTENSIBLE BUSINESS REPORTING LANGUAGE,1,extra level security in credit card,2,face book url,1,face book username,1,facebook,2,fake prize money,3,family pension,9,FAQ,62,faq on fbt on esop,3,FAQ VAT,8,fast facts,1,father can claim for son studies,1,FAX FROM COMPUTER,1,FBT,6,FBT CALCULATOR,3,fbt challan,1,FBT ON ESOP,5,fc(r) ACT,1,fd interest rate,4,fdi in insurance and telecom,4,fdr,13,FEMA,3,FIGURES TO WORDS,2,fii,1,file free etds statement,1,file validation utility,3,Finance,86,finance act,9,Finance Act (2) 2009,2,finance act 2010,1,Finance act 2011,1,FINANCE ACT 2012,4,finance bil 2012,6,finance bill 2010,3,finance bill 2011,3,finance bill in lok sabha,8,finance bill top news,1,finance bill(2) 2009,1,Finance Minister,6,finance ministry,3,financial adviser,6,financial crises,1,financial freedom,1,FINANCIAL PLANNING,23,Financial Services,2,first class rail passenger fare from 01.10.12,3,first discussion paper on gst,5,first name in pan card,2,first quarter fringe benefit tax adjustment,1,fiscal cliff,1,FIVE IN ONE,1,FIVE IN ONE TAX CALCULATOR,1,Fixed deposit,29,fixed maturity plan,8,FLOW CHART ON FBT ON ESOP,3,fm speech on 07/05/2012,1,fmc,1,FMV OF ESOP,3,FMV UNLISTED COMPANY ESOP,2,FN 275-192-2009,1,FOREIGN COMPANT FBT ON ESOP,1,foreign direct investment,1,foreign dividends,2,foreign exchange money changer service tax,3,foreign individual in shares,1,Forensic Auditing,1,Forex derivatives tax,3,forex trading,3,forget password,2,Form 10E,2,form 12BA,1,FORM 16,23,FORM 16 A SOFTWARE,6,FORM 16A,15,FORM 16A FROM ETDS FVU,3,form 16A from fvu,1,form 16a from nsdl,6,FORM 16A GENRETION SOFTWARE,3,FORM 16A PDF,2,fORM 16aA IN FIVE MINUTES,1,form 18 punjab vat act,1,form 26as,37,form 26q,4,form 26q online free,4,form 29C,1,form 49a excel/pdf/online,5,formation of huf,15,forum site,1,FORWARD CONTRACTS ACT 1952,1,fpo,1,fraud mail,4,free auto filler for epayment of taxes,4,FREE CHALLAN SOFTWARE,2,free e filing Income tax return 11-12,2,free epayment auto filler of challan,3,free etds return,12,free etds software,7,FREE INCOME TAX ACT,2,free income tax return,3,free itr-1,8,free itr-2 e filing,3,Free online Books of Direct Tax for F.Y.2008-09,2,free online greeting card holi,1,free samples,2,FREE SOFTWARE,1,FREE SOFTWARE FOR ETDS,4,FREE TOOLBAR WITH SEARCH,2,freelancers,2,Fringe Benefit Tax,2,full partition of huf,2,future and options,8,fvu,8,FVU 2.130,1,FVU 2.131,1,fvu 2.216,1,fvu 3.0,1,fvu 3.2,1,fvu 3.3,2,fvu 3.4,1,GAAR,8,GAIN ON SALE OF SHARES,18,GAR-7,2,gas cylinder,1,GAZETTE NOTIFICATION,4,gdp,1,General anti avoidance rule,4,general insurance,1,general provident fund,1,generation company,1,GIFT BY NRI,6,gift deed to huf,9,gift from relative,15,gift in kind,16,gift on marriage,13,gift tax,21,gig workers,1,gmail,2,Goal calculator,2,gold bond scheme,19,gold deposit scheme,9,GOLD LOAN,11,Gold Monetization Scheme,10,gold silver rates 10 years,5,Goods and Services Tax,22,GOODS TRANSPORT AGENCY ABETMENT,10,goods transport agency service tax,10,GOOGLE SEARCH,1,google tool bar,1,Gopal Kumar kedia,1,got approved from president,1,GOVT NOTIFICATION CST,2,gpf interest rate,5,gpf interest rate 8.6 %,1,gpf interest rate 8.8 %,1,gratuity,14,gratuity limit enhanced,6,Green-channel banking,1,GREETING CARD ONLINE,3,GROSS RECEIPT MEANING 44ab,7,GST,653,GST ADVANCE RULING,1,GST ASSESSMENT,1,GST CHALLAN,8,GST Council,1,GST INVOICE,15,GST ON INSURANCE PREMIUM,1,GST PAYMENT,7,GST RATE CHART,40,GST REFUND,4,GST REGISTRATION,7,GST RETURN,75,GST SUGGESTIONS,3,GST TDS,5,GTA,14,guarantee Nav,1,guidelines for selection of cases,3,gujrat vat act,2,half pay leave,1,HAPPY DIWALI,5,HAPPY NEW YEAR,6,HBA-HRA,8,hdfc bank,5,HDFC Credit Cards,1,Health care,2,Health insurance,19,health plans,4,health service,2,help on tax,1,HIGH VALUE TRANSACTION,6,HIGH-VALUE TRANSACTIONS,3,HIGHER SECONDARY CESS,6,HIGHER TDS WITHOUT PAN 01.04.2010,4,HINDU UNDIVIDED FAMILY,17,hiring motor vehicle,3,holi card,1,holiday,5,holiday on election day,4,holidys,2,Home insurance,5,home loab,1,HOME LOAN,40,hospitals,1,house budget,3,house completion,3,house loan,1,house loan 150000 or 30000,5,house loan and tax svaing,21,house loan at discounted rates,7,house loan on two houses,9,house loan reduuced,2,house property,10,house valuation,5,house wife,2,how to calculate income on salary,1,how to calculate new basic,1,how to calculate new da rate,5,how to claculate income on salary,9,how to file correction statement,6,HOW TO FILE RESPONSE TO INCOME TAX DEPARTMENT,1,how to fill date column in punjab vat form 18,2,HOW TO FILL ITR-2,3,how to fill tds challan 280,9,how to invest in Mutual funds,8,how to pay service tax online,4,HOW TO SELECT ITR FORMS,2,How to use atm,5,HRA and house loan,14,HRA AND TRANSPOT DEDUCTION IN Q4 SALRY RETURN,2,HRA CALCULATION,11,HRA CALCULATOR,11,HRA EXEMPTION,2,HRA EXEMTION,6,HRA FAQ,8,HSC ACC CODE,3,huf and 54B,5,HUF CAPITAL,6,HUF CONTRACT POWER,1,huf creation deed,4,HUF DEFINITION,5,huf formation,5,HUF KARTA,5,huf member name,2,HUF PARTITION,5,HUF TYPE,2,ICAI,66,icai suggestions,6,ICAI tool bar,5,ICDS,2,ICES,1,ICICI Bank's credit card,1,ICICIBANK CREDIT CARD,8,idfc infra bonds,3,ifci,3,IFRS,4,ifsc,1,iifl,2,immovable property,12,IMPACT OF GST,71,implementation of report,2,import,3,IMPORTANT DUE DATES,7,imps,2,INCOME FROM HOUSE PROPERTY,26,Income from Mutual funds.,14,income from other source,1,income from share equity,15,income processing pending,1,Income tax,13,income tax slabs fy 2008-09,1,INCOME TAX ACT,2,INCOME TAX ACT EBOOK,2,income tax act tds 194C,3,Income tax benefit in budget,1,INCOME TAX CALCULATOR,23,INCOME TAX CALCULATOR 09-10,5,income tax calculator 12-13,2,Income tax calculator 2011-12,3,income tax case selection,1,income tax changes in budget 2010,1,income Tax circular,2,income tax circulars from 1961,1,income tax code 2009,1,income tax department,1,income tax due date extended,5,INCOME TAX FORM FILLABLE,1,income tax forms,5,income tax help tool bar,2,income tax notice on late deposit of tds,1,Income tax notification,4,income tax notification from 1961,1,income tax office,4,income tax payment through atm,1,income tax rate chart. i tax rates 12-13,3,income tax rates after budget 2012,2,income tax rates fy 2013-14,1,income tax refund,34,income tax return,63,INCOME TAX RETURN 16-17,15,INCOME TAX RETURN 20-21,11,income tax return 2011-12,9,INCOME TAX RETURN 2015-16,65,Income Tax return 23-24,2,INCOME TAX RETURN AY 18-19,15,income tax return due date,20,INCOME TAX RETURN EXEMPTION,6,income tax return form,5,INCOME TAX RETURN FORM 12-13,16,INCOME TAX RETURN FORM EXCEL,4,income tax return form itr-2,1,income tax return last date,5,Income tax rules,7,INCOME TAX SLAB,14,income tax slab in dtc,1,income tax slabs,7,INCOME TAX SLABS AFTER BUDGET,4,income tax ules 9th amendment,1,INCOME WISE ITR FORMS,2,INCOME-TAX-RETURN-AY-17-18,18,INCOMETAX 6TH PAY,2,inconsistancies in etds returns,10,inconsistencies in etds returns,3,IND AS,1,ind-as,3,INDEMNITY BOND,1,India against corruption,3,india budget,2,INDIA VS AUS,1,India win world cup,1,INDIAN BANK CHARGES,7,INDIAN INCOME TAX CALCULATOR 2007-08,1,indian rupee,3,indirect tax proposals,4,INDIVIDUAL HUF TAX RATES,5,indusind bank,1,INFLATION INDEXED NATIONAL SAVING SECURITIES,1,infosys,1,infra bonds limit increased,1,infrastructure Bonds,13,inoperative accounts,8,INPUT SERVICES,4,INPUT TAX CREDIT,19,instruction no 9/2010,1,INSTRUCTION TO FILL ITR-2,1,Insurance,16,insurance claim,2,insurance of bank deposit,1,Insurance policy,10,intangible assets,1,INTER BANK MOBILE TRANSFER,7,inter haed loss adjustment,3,interest,1,interest free laon,2,Interest from bank,3,interest on borrowing capital,3,INTEREST ON HOUSE LOAN,37,INTEREST ON LATE DEPOSIT,13,INTEREST ON LATE GRATUITY PAYMENT,1,interest on ppf account,16,interest on self occupied house,2,interest on small savings,10,interest rate on late deposit,3,interest rate on tds late deposit,4,interest taxable on saving,3,interim budget,7,internal auditor,1,international taxation,7,INTIMATION U/S 143(1),6,Investing,6,Investment,5,investment in shares,2,Investment management,6,investment yogi,1,IPL 2011,1,ipo,5,IRDA,22,irds,1,it calculator 2009-10,1,itat,5,Itax calculator ay 2011-12,2,itax calculator fy 10-11,1,itns 280,2,itns 281,1,itns 282,1,itns 283,1,itns281,2,itr -3 excel 2010-11,1,ITR 11-12,2,itr 2 excel,2,itr 2 rpu,3,ITR 23-24,1,ITR 24-25,6,itr 4 e filing utility,4,itr 4 fy 2010-11,1,itr 4 rpu,1,ITR AY 18-19,15,ITR EFILING SOFTWARE,10,ITR FORM 12-13,5,itr form 13-14,16,itr form 2 ay 2011-12,1,itr form 2008-09,4,itr form 2011-12,4,itr form 2013-14,1,ITR FORM AY 19-20,7,ITR FORM SAHAJ,18,ITR FORM SELECTION,4,ITR FORM SUGAM,6,itr forms,24,itr forms ay 2009-10,4,ITR RPU 2010-11,2,ITR RPU AY 2008-09,2,ITR RPU AY 2009-10,1,ITR SOFTWARE,3,itr sugam,7,ITR V STATUS,4,ITR WORD FORMAT,1,ITR-1,4,itr-1 2010-11 ay,6,ITR-1 EXCEL 08-09,2,ITR-1 EXCEL 11-12,1,ITR-1 rpu in excel free,1,ITR-2 AY11-12,2,ITR-2 EXCEL 08-09,2,itr-2 excel 2010-11,4,ITR-2A,1,ITR-3 EXCEL 08-09 AND ITR 4 EXCEL 08-09,1,itr-3 rpu,1,itr-4 efiling .itr-5 efiling,6,ITR-4S SUGAM,6,ITR-5 EXCEL,2,itr-6,1,ITR-7,2,ITR-V,27,itr-v status,19,ITUR FORM SUGAM,1,jan 2012 da rate,3,jan lokpal bill,5,jan lokpal vs lokpal bill,2,JAVA BASED INCOME TAX RETURN FORMS,1,JCO,1,Jewellery,6,job switch,2,Job work,11,joint employment,1,joint name,5,judicial decision,1,karnataka high court case,5,key highlights,1,kisan vikas patar,4,KKC,3,KNOW ALL ABOUT TDS,1,KNOW PAN STRUCTURE,7,know the ip address of sender yahoo mail,3,KNOW YOUR,10,KNOW YOUR CST NUMBER,5,know your customer,6,KNOW YOUR DIVISION CODE,1,know your epf balance,12,know your ip address,1,KNOW YOUR LOCATION CODE,2,know your pan,28,know your pan address,2,KNOW YOUR PPF,12,know your refund status,20,KNOW YOUR REFUND STATUS ONLINE,10,KNOW YOUR SERVICE TAX NUMBER,9,know your tax deducted,2,know your tax deposited,2,KNOW YOUR TIN,8,KNOW YOUR VAT/TIN NUMBER,4,Krishi Kalyan Cess,15,krishu kalyan cess,1,KV Kamath,1,kvp,7,kyc,13,Labour Codes,4,LAHMAN BROTHERS,1,land lord pan must,3,laptop,1,LARGE TRANSACTION,3,last date to deposit tds,1,LAST DATE TO FILE ETDS RETURNS,2,last date to file itr 2007-08 extended,1,late deposit of tds,2,LATE FILING OF ITR-V,20,late funishing of return,5,late payment of service tax,4,latest depreciation rates,9,latest income tax circulars,1,latest income tax notification,1,latest notification,3,latest tds rate chart,25,leave,2,leave encashment,10,LEAVE TRAVEL ASSISTANCE,7,Leave Travel concession,8,legal heir,1,less,1,liaison office,1,lic,8,lic agent,1,lic jeevan vaibhav,1,LIC JEEVAN VRIDDHI,2,lic table 145,1,Life insurance,49,life insurance agent,10,life insurance broker,4,LIFE INSURANCE POLICY,41,LIFE INSURANCE POLICY AND TAX SAVING,21,LIFE INSURANCE PREMIUM,19,Limit for court case,3,Limit of gratuity under income tax,6,LIMIT UNDER SECTION 44AF,2,LIMITED LIABILITY PARTNERSHIP,8,LIQUID FUNDSS,1,liquidity crises,2,list of taxable service,2,LIVE BUDGET STREAM 2011,1,LLP,9,LLP RATES,1,loan against fdr,4,loan against property,2,loan eligibility,2,loan for higher education,3,LOAN ON PPF,5,loan repayment period calculator,1,LOAN RESOLUTION,1,LOAN SECURITISATION,1,Lok sabha election results/trends all states and all seat,4,lokpal bill,2,long term capital gain,24,low cost laptop,1,lpg,6,lt infra bonds,1,LTC BY AIR,7,LTC OUTSIDE INDIA,2,LTCG,12,lucknow chartered accountants,1,macro,2,Mahila Samman Bachat Patra,2,mail frauds,1,mail scams,1,mandap keeper,5,mandatory e filing service tax return,15,mandatory epayment of taxes,12,Manoj Agarwal,9,manpower,9,marked to market,1,marketable product,1,MasterCard,6,mat,3,maternity leave,3,MCA-21,15,McDowell and Co. Ltd. (154 ITR 148),1,meaning of transfer in capital gain,1,meanings of finance terms,6,medical insurance premium,14,MEDICAL OFFICER,3,medical u/s 80D,28,MEET,1,MENREGA,1,merge ledger in tally,1,MICR CODE,5,Microsoft,5,Microsoft Excel,7,military pay,2,minimum alternative tax,9,minimum balance,5,minimum experiance for bank branch auditor,1,minimum experience for bank branch auditor,1,minimum service,1,minimum wages,5,Minor income,3,mip,1,mis matching,12,MISTAKES IN ETDS RETURN,5,mistakes in itr,3,mistakes in return filling,3,MIXED SUPPLY,2,Mobile Number Portability,5,MOBILE WALLET,1,Money,3,Money Mistake,3,monthly income plans,3,monthly income scheme,8,MOTOR INSURANCE,2,MRTP,2,ms excel,1,MS OFFICE,2,MSME,5,multipal challan,2,multiple pan,2,Mutual Fund,63,mutual funds and tax,29,MVAT AUDIT,7,mvat audit form 704,4,myth vs Real,1,Nabard Bonds,2,NACH mandate,1,name break up in pan,1,nandan nilekeni,1,NATIONAL ELECTRONIC FUND TRANSFER,1,National Identification Authority,1,National pension scheme,1,NATIONAL SAVING CERTIFICATE,3,NAV,1,NEFT,14,NEGATIVE LIST FOR TAX ON SERVICES,31,Net asset value,3,net banking,3,new excise return form,3,new 194 c,5,NEW BASE RATE INTEREST,1,NEW BASIC AND GRADE PAY,2,new basic formula,1,new coin,1,new cut off limit for TDS,2,new da rate,10,new deduction,3,NEW EST-1,1,new etds requirement,1,NEW EXCISE DUTY ITEMS,2,New Foreign Trade Policy,4,NEW FORM ITR FY 2010-11,1,new fuv 2.110,1,new fvu 2.128,3,new income tax act,1,new income tax calculator,5,NEW INCOME TAX RATES,31,new income tax return form 2010-11 itr-1,3,new income tax return form 2010-12 itr-1,1,New Infosys Chairman,1,new itr form,6,NEW ITR FORM AY 2011-12,3,new itr forms,14,NEW ITR FORMS EXCEL,6,new jeewan dhalan,2,NEW PAN APPLICATION,13,NEW PAN CARD,8,NEW PARTNER ADDED,1,NEW PAY BAND,2,NEW PAY SCALE FOR UNIVERSITIES COLLEGES,1,NEW PAYSCALE FOR PROFESSOR LIBRARIAN DPE,1,New pension scheme,2,new pension scheme to govt employee,16,NEW RUPEE SYMBOL,5,new rupee symbol font,2,new sahaJ tax form,5,new section 44AF,2,new service tax rate 12.36,6,NEW SERVICES UNDER SERVICE TAX,8,new tax form,1,NEW TAX RATES,6,new tax regime,2,new tds rate 2010-11,10,new tds rates fy 2009-10,11,new tds rules applicable.,8,NEW TDS RULES FY 2010-11,4,New Year's Day,1,newly weds,1,nhai bonds,4,nhai capital gain bond,4,nhai tax free bonds,4,nifty,1,nil etds challan,4,nil etds return,5,nil tds on transportor,5,Nishant Batra,2,no return for salary,2,No.402/92/2006-MC (10 of 2008),1,nomination,1,non deduction certificate,1,non deposit of TDS,1,non performing assets,1,NON RESIDENT INDIAN,16,NOR,1,note security features,3,NOTES ON 3CD,10,notice of meeting through email company,1,notice pay,5,notices etds,2,notification 19/2008 service tax,1,Notification 19/2009-ST,1,notification 22/2011,1,notification 23/2011,1,notification 24,1,NOTIFICATION 25/2012,7,Notification 26/2011,1,notification 3-2011,1,notification 32/2009 dated 27.03.2009,1,NOTIFICATION 36/2011,2,NOTIFICATION 41 DT 31.05.2010,1,notification19.03.2012,2,npa norms,3,NPCI,1,NPS,42,NPS vatsalya,1,NRI,29,nri investment indua,4,NRI.PIO,17,NSC ACCRUED INTEREST,16,NSC INTEREST CALCULATOR,9,nsc.,12,NSDL,4,NSE,2,NUMBER TO TEXT,1,numbers in to text,1,OCI,3,official notification,1,official website,2,oidar,1,oltas,4,one increment,2,ONE RANK ONE PENSION,1,one thousand rupee note,2,online,1,ONLINE BALANCE CHECK EPF,4,online bsnl bill verification,2,online deposit of tax,7,online earning,1,online emi calculator,1,online employee provident fund,3,online epf balcnce,8,online filing of service tax return,14,ONLINE FOREX TRADING,1,online life insurance,6,ONLINE PAN,3,online pan verification,3,online rectification itr,2,online refund,16,ONLINE REFUND STATUS,7,ONLINE REGISTRATION OF COMPANY,2,online return rectification,2,online service tax,2,online services by Govt,1,ONLINE ST-3,7,online tan regsitration,6,online tds payment,4,ONLINE VAT,2,opc,2,OPEN OFFER,1,option date,2,orop,1,other forms,1,other income to employer,4,out of debt,2,OUTPUT SERVICE TAX CREDIT,1,OUTSTATION CHARGES,2,own name,1,PACKAGE SOFTWARE,2,PAN,6,PAN ADDRESS,5,pan and income tax return,1,PAN AO CODE,6,pan application excel,4,pan correction,2,pan details,1,PAN LEDGER,8,pan login,7,pan mandatory for hra,2,pan mandatory in etds,2,pan name verificatio,3,PAN ON RENT RECIPT,1,pan regsitration,2,PAN STATUS NSDL,2,PAN STATUS UTI,1,PAN STRUCTURE,4,PAN SURRENDER,2,pan transfer,1,pan verification,8,pan vs return,1,parcel,1,PARNERSHIP,1,part time course tuition fees,3,part of the year employee form 16,2,part of the year employee form 24q,3,partial reverse charge in service tax,25,partial withdrawal,3,partner salary,5,PARTNERSHIP DEED,5,PARTNERSHIP RATES,1,passport,1,PASSWORD,4,PATENT,1,pay bands,3,Pay calculator,3,pay calculator revised,1,pay commission punjab,1,pay fixation examples,2,pay per post,1,PAY SERVICE TAX ON DUE BASIS,5,payable at par,1,paybands,1,payment bank,1,PAYMENT BY ACCOUNT PAYEE CHEQUE,4,payment by cheque income tax,2,payment due date reminder,1,payment exceeding 20000-35000,1,payment of gratuity act,6,paypal,1,paypal ceiling,1,PDF UTILITY,4,penalty for service tax,8,penalty if cheque cleared late,4,penalty on concealment of Income,7,penalty on late filing non filing of etds return,8,penalty on late filing of income tax return,21,pension,14,pension arrear,2,pension calculator,4,pension da,1,pension fitment,1,pension gazette notification,1,pension notification,1,pension on grade pay military pay,2,pension policy,3,pensioner benefit,3,Permanent account number,8,PERSONAL ACCIDENT INSURANCE,4,personal finance,9,personal finance software,3,personal loan,6,PETROL DIESAL SAVE FISCAL DEFICIT,8,PETROL DIESEL PRICE HIKED,12,PETROL EXPENSES VALUATION,8,petrol prices reduced,5,PFC,1,PFC INFRA BONDS,2,PFC TAX FREE BONDS,2,pfrda,2,PHONE BANKING,2,phone password,1,pin,1,pivot tables,3,Place of Provision of Services Rules,4,PLAYER AUCTION,1,pmay,7,pmjdy,11,PMS,2,pmvvy,2,pnr,1,Point of sale,8,POINT OF TAXATION,45,political party deduction,2,Poppy Seeds,1,portfolio,1,POST GRADUATE TEACHER,1,post office fixed deposit,9,post office recurring deposit,11,post office saving deposit account,6,post office schemes,15,postal ballots,1,postal order,2,POWER FINANCE BONDS,2,POWER OF ATTORNEY,1,PPF,40,PPF CALCULATOR,16,ppf huf account,4,ppf interest rate,19,ppf limit,25,ppp,1,ppt,8,ppt fbt,3,ppt on budget 2011,1,PPT UP VAT,1,pranav mukharjee,1,pre construction interest,3,PRE EXISTING E-1 TRANSACTIONS,1,pre filled challan income tax,1,prepayment,1,prepayment penalty,4,press release,1,press release 14.08.2008,3,presumptive tax scheme,17,preventive health check up,4,PRIMARY TEACHER,1,PRINCIPAL,1,printing manual,1,private limited company,10,PROF. TAX,1,profession tax,2,PROFIT RATE UNDER 44AF,1,provident fund dues,1,PROVISION OF FBT ON ESOP,1,provisioning of npa,2,PSPCL,1,PSTCL,1,PSU PAY HIKE,2,public limited company,2,public provided fund,9,PUBLIC SHARE HOLDING IN LISTED COMPANY,2,punjab govt arrear calculator,1,PUNJAB VAT,21,punjab vat notification,16,purchase of residential house,1,pure agent,1,qfi,1,quarterly statement status,3,QUIZ,9,rail freight,6,railway budget,12,railway budget 2012,2,railway ticket,9,RAILWAYS BUDGET 09-10,2,RAILWAYS BUDGET 11-12,1,rajiv gandhi equity saving scheme,13,RAJKUMAR S ADUKIA,4,ramalingam,15,Rate of return,1,RATES AFTER BUDGET,1,rates of service tax,3,rbi,84,RBI ACT,22,RBI Circular on e-payment of taxes,2,RBI FALSE CALLS,9,RBI FALSE MAIL,5,RBI INSTRUCTIONS GAR-7,1,RBI MONETARY POLICY,13,rbi monetary policy 2012,2,RBI NOTIFICATIONS,7,rbi report on customer services,2,ready reckoner income tax,4,REAL ESTATE,10,Real Estate Investments,4,REAL TIME GROSS SETTELEMENT,1,reason for mis matching,6,REBATE ON INPUT GOODS AND SERVICE,3,REC Bonds,3,rec infra bonds,1,rec tax free bonds,2,recent,210,rectification of return online,4,reducction in crr,1,refinance calculator,3,refund,8,refund due to diff in valuation of perquisites,3,refund of service tax on cancellation of tickets,4,refund pilot scheme,4,refund without matching,6,registration charges tax saving,1,RELIANCE COMMERCIAL FINANCE,1,RELIANCE GOLD LOAN,3,RELIANCE LIFE INSURANCE,3,RELIANCE MUTUAL FUNDS,1,relief calculator 2010-11,1,relief calculator fy 2011-12,1,REMUNERATION TO PARTNERS,8,RENT,1,rent a cab,2,RENT RECIPT,1,RENTING OF IMMOVABLE PROPERTY AFTER 01.07.2012,8,RENTING OF IMMOVABLE PROPERTY AFTER BUDGET 2010,5,repayment of housing loan,1,REPLY TO CPC FOR NOTICE,13,REPO RATE,12,Reserve Bank of India,2,reset password,1,RESIDENTIAL STATUS,4,RESOLUTIONS,1,response to outstanding demands,3,RESTAURANT,10,restricted leave,1,retail investor,4,retirement planning,11,retirement steps,2,Retiring early,1,retrospective amendment,1,RETURN EXEMPTION SALARIED CLASS UP TO 5 LAKH,6,RETURN FILING DATES,1,return filing in odd conditions,1,return for contractors tax deducted,1,return not required with pan,1,return of income,1,RETURN PROCESSING,4,RETURN UP TO 5 LAKH,5,RETURN UPTO 5 LAKH,2,REVENUE STAMP ON CHEQUE PAYMENT,4,REVENUE STAP ON RECEIPT,1,reverse charge on works contract,17,REVERSE CHARGE GST,57,reverse charge of service tax,43,reverse mortgage,3,reverse of 80C benefits,3,REVERSE REPO RATE,12,REVISE RETURN,4,revised option date,1,revised pay calculator,3,revised return,7,REVISED SCALE,1,rewards,1,rgess,9,rich,1,right to reject,2,RPF,5,rpu,9,rpu 1.7,1,rpu 2.2,2,rpu 2.5,1,rpu 2.7,1,RPU 3.00,1,rpu 3.1,1,RPU ITR 2011-12,1,rpu2.8,1,RTGS,16,rti,2,rti fees,2,rule 12 of income tax return.,10,RULE 2A,1,rule 4A,2,rule 6(4A),1,rule 6(b),2,rule 6DD,6,rule of 72,1,rule3,2,rule40BA,1,Rupay,2,RUPEE SYMBOL,4,s,1,safety tips for atm,4,SAHRE SHORT TERM CATIAL GAIN,7,salaried employees,3,salary calculator,7,SALARY ETDS Q4,5,salary in new direct tax code,1,salary structure,3,salary tds,9,sale in transit,4,sale of agriculture land,8,SALE OF DEBENTURE,1,sale of residential house,2,SALES MEANING 44AB,5,Sales tax,1,samsung case,3,saral 2,3,saral II,1,SARAL II IN EXCEL,1,Satyam,1,Satyamevjayate,1,SAVE TAX,2,SAVING ACCOUNT,7,saving bank interest,18,saving bank interest rate,2,saving linit u/s 80c,8,saving more than income,2,SAVING PASSBOOK,1,sbi 9.75 % bonds,1,SBI bonds,1,sbi home loan,4,SBI interest rates,10,sbi net banking,4,sbi rates,6,SBIOAHC,1,SBS WIKI,1,SCAM,2,schedule VI companies act,2,SCOPE OF ETDS STATEMENT,1,SCOPE OF SERVICE ENLARGED,1,SCOPE OF SERVICES WIDENED,1,scrutiny fy 11-12,3,scrutiny selection,18,search income tax,5,seat wise/constituencies wise and party and party candidate wise latest position,1,sebi,24,SEC 194 C,5,SEC 194 I,10,sec 194 J,4,secion 80c,4,SECRETARIAL STANDARD,3,secrutiny of itr,1,section 10(10AA),1,SECTION 10(13A),4,section 10(38),3,SECTION 10(5),1,section 139(1),1,section 139(4),1,section 139(5),1,Section 14,1,SECTION 145,3,section 154 return online income tax,4,section 16(iii),1,section 189,1,section 192,8,section 194-J,6,SECTION 194A,4,section 195,11,SECTION 195A,1,section 197,5,SECTION 2(37A),1,section 201(1A),3,section 203(3) section 206(C)(5),5,section 205,1,SECTION 24(b),8,section 269SS 269T,6,section 270A,5,section 271(1)(c),1,section 282B,1,Section 36(1)(vii),1,section 40(a)(ia),13,SECTION 40A(3),13,section 43(5),1,SECTION 44AB 2007-08 LAST DATE,4,section 44AB limit,14,SECTION 44AE,6,SECTION 44AF,2,Section 50,1,Section 50C,2,section 54,30,section 54f,9,SECTION 60,1,section 616(c),1,SECTION 64,2,section 66B service tax,4,section 68,2,Section 73,1,section 80 M,2,section 80c,3,section 80CCF,7,section 80D,18,section 80E,9,secured code master card,5,Securities and Exchange Board of India,1,security features,1,sehaj,1,self assessment tax,5,Seminar on service tax changes,1,Senior citizen,19,Senior Citizens Savings Scheme 2004,19,service charge,3,service ta,1,SERVICE TAX,45,service tax code,1,Service Tax (Removal of Difficulty) Order,1,SERVICE TAX 2010,1,service tax ac class,1,service tax accounting code,5,service tax adjustment,1,service tax audit,10,SERVICE TAX CHANGES FROM 01.07.2012,46,service tax changes in budget,58,Service TAX CLARIFICATION,17,SERVICE TAX COMPLIANCE,1,SERVICE TAX DEPOSIT DUE DATE,9,SERVICE TAX DUE DATE,6,Service Tax excel pdf word,1,SERVICE TAX EXEMPTION LIMIT,9,Service Tax Form excel pdf word,3,SERVICE TAX FORMS,1,service tax internet banking,1,service tax notifications,5,SERVICE TAX ON LAW FIRM ADVOCATES,3,service tax on transportation of passengers by air,2,service tax on advocates,5,SERVICE TAX ON BROKERAGE,2,service tax on ca,2,service tax on coaching,4,service tax on construction services,23,service tax on director services,5,SERVICE TAX ON DISTRIBUTION OF ELECTRICITY,2,SERVICE TAX ON EDUCATIONAL SERVICES,4,service tax on gta,7,service tax on health services,4,service tax on hotel clarification,12,SERVICE TAX ON HOTEL ROOM RENT,10,service tax on invoice basis,5,service tax on lawyers,1,SERVICE TAX ON LEASING,1,SERVICE TAX ON PACKAGE SOFTWARE,1,service tax on railway freight,8,SERVICE TAX ON RENT,6,service tax on road,4,service tax on transmission distribution of electricity,4,service tax on work contract tax,9,service tax on wrong head,1,service tax onr eimbursements,1,SERVICE TAX PAYMENT,6,SERVICE TAX PROCEDURES,3,SERVICE TAX RATE CHART,12,service tax rate effective date,12,service tax rate reduced,5,service tax rates increased,21,SERVICE TAX REGISTRATION,12,SERVICE TAX REGISTRATION LIMIT,4,SERVICE TAX RETURN,34,SERVICE TAX RULES,11,service tax section 65(105)m,1,SERVICE TAX VOLUNTARY COMPLIANCE ENCOURAGEMENT SCHEME,17,SERVICES CHARGES OF BANKS,2,SERVICES TAXABLE,5,servicetax,1,set off in same head or other head.,11,sevice tax on associate enterprises,2,sez,6,share,3,share market,4,SHARE SHORT TERM Capital GAIN,11,share transfer,1,share your thoughts,1,SHOME COMMITTEE REPORT,3,Short term capital gain depreciable Assets,1,SHORT TDS,1,SHORT TERM ACCOMMODATION,2,short term capital gain 15 %,10,silver,1,SIM CARD,2,simple interest,1,SIMPLE TAX CALCULATOR,2,single premium policy,2,sip,12,SIXTH COMMISSION,2,sixth pay commission,17,skimming,1,slider based EMI calculator,1,SLR,4,small finance bank,1,small saving schemes,20,small service provider,1,smart buying tips,1,software import,1,son eduction loan father,1,speak asia,3,speak asia fraud,2,speak asia online,2,speed clearing,3,spending habits,1,SPF,8,splitting of wages,2,spouse income,1,Spreadsheet,2,SRVICE TAX CLARIFICATION,9,ss patta,1,ST-1 EXCEL,4,ST-2,2,ST-3,12,stamp duty,3,STANDARD DEDUCTION,6,standing committee,1,startup india,2,State Bank of India (SBI) Cards,1,status of return,1,STATUS OF TAX DEDUCTED,1,statutory audit,8,stay on demand notices,4,STCG 10% 15%,13,STGC,1,Stock,1,STOCK EXCHANGE,1,STOCK MARKET FROM 9.00 AM.,1,STOCK MARKETS,1,stp,1,STRUCTURE AND VALIDATION OF PERMANENT ACCOUNT NUMBER,2,stt,7,stt challan,1,sub contractor,3,SUBPRIME CRISES,2,success secrets,1,sugam,5,Suggestion on Budget-23,35,Sukanya Samriddhi Account,11,SUPREME COURT,2,SUPREME COURT RENT,7,sur name in pan,1,surcharge cess on tds,4,Surrender-Cancellation of Service Tax Registration,1,survey income tax,5,SWACHH BHARAT CESS,12,swiss bank,1,SWP,1,Systematic Investment Plan,8,tally 7.2,3,tally 9,5,tally easy,3,tally erp9,6,tally recycle bin,3,tally shortcut,10,tally simple,8,tally tips,5,TAN,3,TAN STRUCTURE,1,Tariff Value,1,Tax saving,4,tax accounting standards,4,TAX AMNESTY SCHEME,4,tax benefit from budget,2,TAX CALCULATION,4,TAX CALCULATION 2008-09,1,TAX CALCULATION FORMULA ADDIN EXCEL,2,TAX CALCULATOR,1,tax calculator 10-11,2,TAX CALCULATOR 2008-09,1,tax calculator 2010-11,2,tax calculator after budget 2011,1,tax calculator financial year 10-11,1,tax calculator fy 11-12,1,tax calculator income tax,1,tax collection,3,Tax credit,5,TAX DEDUCTED AT SOURCE CALCULATOR (TDS)2007-08,2,tax deducted at source return etds,3,Tax deduction,8,tax deduction at source chart,1,TAX EVASION,1,Tax free bonds,7,tax harvesting,1,Tax information summary,1,TAX ON ARRERS,1,tax on due date by cheque,2,tax on perquisite,4,TAX ON PROVIDENT FUND,2,tax payment by internet,1,tax payment from other's account,1,tax payment online,1,tax planning for salary,5,TAX RATES,2,tax rates changes in budget 2011,2,tax rates in new tax code,2,tax return preparer,1,tax saving capital gain,3,tax saving mutual funds,17,tax saving tips,1,TAX SLABS,7,tax through atm,2,tax yogi,3,taxable allowances,6,Taxation,1,Taxation in India,1,TAXES BY INTERNET,1,TAXMANN,4,taxpayer information summary,1,TAXPRO CHALLAN,2,tcs on gold,12,tcs on jewellery,8,TCS ON MINERALS,2,tcs rate chart,5,TCS RATES,18,tds certificate,2,tds 194I Limit for deduction,7,tds at less rate,6,tds calculations,2,tds calculator,11,tds calculator after 1.10.2009,1,TDS CERTIFICATE,6,tds challan 281,5,tds chart,1,TDS CORRECTION,3,TDS CREDIT MORE TAN ONE YEAR,4,tds cut off limit changed,1,tds deducted in march,8,TDS DEFAULT BY EMPLOYER,2,tds deposited on time,2,tds due date,5,tds man,4,tds matching,5,tds noitce,1,tds not deducted penalty,5,tds not paid,1,TDS ON BANK INTEREST,1,tds on car charges,1,TDS ON COLD STORAGE RENT,5,tds on commission,3,tds on discount on prepaid cards,1,TDS on e-commerce,1,TDS ON EPF,2,tds on fees,1,TDS ON GST,6,tds on immovable property,19,TDS ON INTEREST,5,tds on job work,2,tds on Non resident,10,tds on players,3,tds on professional services,6,tds on rent,13,tds on royalty,6,TDS on salary,36,tds on sale purchase of property,2,tds on service tax,9,tds on service tax on professional services,4,tds on service tax u/s 194-J,7,tds on taxi hire charges,4,tds on technical services,1,tds on transporter,5,tds on transportor,2,tds on travel agent,1,tds on umpires,1,tds on vehicles,2,tds online,1,tds payment online,1,tds payment online mandatory,2,TDS PRESENTATION,1,tds professionals,1,TDS PROVISIONS,1,TDS RATE 10-11 -TDS DEPOSIT TDS RETURN DUE DATE DOWNLOAD PDF,3,tds rate 2011-12,1,tds rate 2012-13,5,tds rate after budget,4,tds rate chart,18,TDS RATE CHART 11-12,5,tds rate chart 2019-20,1,tds rate chart fy 2014-15,1,tds rate chart fy12-13,1,TDS RATE WITHOUT PAN,3,TDS RATES,33,tds rates 07-08 EXCEL,3,tds rates 09-10 FY,6,TDS RATES 10-11,11,tds rates 2012,4,tds rates after budget 2010,2,TDS RATES ASSESSMENT YEAR 2011-12,4,tds rates chart 10-11,2,TDS RATES DIRECT TAX CODE,2,TDS RATES FOR AY 2010-11,2,tds rates fy 2016-17,3,TDS RATES FY 2017-18,3,TDS RATES FY 2018-19,1,TDS REFUND,11,tds return online free,3,tds rules amendment,4,tds salary rate,3,tds section 194C,9,tds software,1,tds statement,2,tds taxi charges,2,tds u/s 194C,7,TDS U/S 195,8,tds verification,2,TDSCPC,28,tdsman,15,tdsman software,13,TEACHER PAY SCALE,1,TERM DEPOSIT,3,TERM INSURANCE,9,term plan,2,The companies act 2013,132,The companies rules,115,THIN CAPITALISATION,1,third party insurance,2,ticket booking tds,2,time deposit,2,times prime membership,1,TIMING CHANGE,1,tin structure,2,tin-nsdl,14,tin-nsdl free etds statement software,3,TIN-NSDL.TIN NSDL FORM 16,4,TIS,1,TOLL FEES,1,tool bar for Chartered Accountants,5,TR-6,1,traces,15,TRADEMARK,2,trading in shares,7,transaction not transfer,1,transfer fee,1,transfer includes,2,transfer loan from one bank to other,1,transport allownace,6,transport of goods by rail,5,travel agent tds,1,tribunal,1,trp,1,tuition fees,7,tuition fees children,2,TURNOVER MEANING 44AB,8,two challan in same month,1,uan,12,ubislate,1,UDYAM PORTAL,1,UGC PAY SCALES,1,uid,10,uidai,5,ulip,30,ULIP AFTER BUDGET,6,ulp,2,unclaimed deposits,6,undeliverd refund status,1,undelivered refund status,4,uniform allowance,2,union budget 2010,1,union budget 2011,2,union budget 2012,5,union budget 2012-13,29,unique identity number,5,unique tds certificate number,2,Unique trasaction number,3,unit linked insurance plan,6,UNIVERSAL ACCOUNT NUMBER,3,universal life plans,1,unsecured non convertible debentures,4,up election,3,UP VAT,2,UPI,2,USA,1,use of tally,1,uti pan card,3,UTN,5,V S Vadivel FCA ACS,1,vacant house,1,valuation of motor car,5,valuation of perquisites,16,valuation of perquisities,11,valuation of rent free house accommodation,5,valuation of works contract 01.07.2012,11,VALUE ADDED TAX,5,VAT,8,vat 11 digit detail,2,VAT ACT,3,VAT AND SERVICE TAX ON SOFTWARE,2,VAT DEFULTERS,1,VAT FORMS,2,VAT LATEST RULES,3,VAT MEANING,1,VAT NUMBER PUNJAB,1,vat on petrol,3,vat rate 4 to 5 %,1,vat rate changes punjab,3,VAT RATES,2,VAT RULES,1,VAT SCHEDULE,1,VAT TDS ON WORK CONTRACT,4,VAT UP AT A GLANCE,1,VCES,7,verified by Visa,3,VERIFY EXCISE CODE,1,verify pan,2,VERIFY SERVICE TAX CODE,7,VERIFY YOUR SERVICE TAX DEPOSIT,1,video,14,VIEW 26AS,7,VIEW YOUR TAX CREDIT,6,view your taxes online,5,Visa,4,VISHAL-REHEJA,1,vodafone,2,WAGES,3,ward circle,2,wealth tax,8,WEBCAST OF BUDGET 2011 ON COMPUTER,2,weighted scientific research deduction,2,what do u mean by micr,2,what does 10 digits of pan card indicates,1,what does each letter in pan number indicate,1,WHAT IS CHEAPER,1,what is company code 0020,1,WHAT IS DEARER,1,what is micr code,2,what is neft,8,what is PAN,1,WHAT IS STC,3,what is the meaning of rtgs,6,whatsapp,1,WHEAT AND PADDY,1,white paper,1,who can file sahaj.,11,who can sign income tax return,2,who can use itr-2,5,WIFE'S POLICY PREMIUM,2,wifes name,2,WILL,5,window dressing,1,without consideration,1,work contract service tax,16,working capital,1,Workmens Compensation Act,3,WORKS CONTRACT,3,wrong accounting code in service tax,1,wrong assessment year in challan,4,wrong head on challan,2,wrong name error in e filing registration,7,WRONG NAME IN ETDS RETURN,2,wrong pan on challan,2,wrong pan while deposit,1,wrong section on challan,3,www.satyamevjayate.in,1,xbrl,5,XLSX,2,ynitya income tax calculator,22,YouTube,1,
ltr
item
SIMPLE TAX INDIA: LEVY OF GST ON LIQUIDATED DAMAGES
LEVY OF GST ON LIQUIDATED DAMAGES
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjV9iZgNaLXXPTufjUlGDKyu4LUx0SUgvZzCHxs9rWwiO1HWN1hYmv89C5XyNMNmEfj-UvgTjqKBZ3UOdr9_TEbc7cvMHZU5teFhvyGN1KvC1DONDtdfYsLxRQFw9qYjzeiguQ6UvmMwZIk/s1600/LIQIODATED+DAMAGES.png
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjV9iZgNaLXXPTufjUlGDKyu4LUx0SUgvZzCHxs9rWwiO1HWN1hYmv89C5XyNMNmEfj-UvgTjqKBZ3UOdr9_TEbc7cvMHZU5teFhvyGN1KvC1DONDtdfYsLxRQFw9qYjzeiguQ6UvmMwZIk/s72-c/LIQIODATED+DAMAGES.png
SIMPLE TAX INDIA
https://www.simpletaxindia.net/2018/09/levy-of-gst-on-liquidated-damages.html
https://www.simpletaxindia.net/
https://www.simpletaxindia.net/
https://www.simpletaxindia.net/2018/09/levy-of-gst-on-liquidated-damages.html
true
2004257931445490362
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy Table of Content